A KPMG assurance report on Waikato Regional Council's "Project Reboot" enterprise software rollout notes significant improvements from an earlier review, but costs have risen.

The latest KPMG project assurance report, posted in a committee agenda, uses a red/amber/green scale to rate the risk level of various aspects projects and their governance.

Where a review conducted last November found seven high risk issues, defined as "potential showstoppers", the latest report, found three: resource and progress management; cost management, and; transition and support.

Amber rated aspects of the project, denoting medium risk issues, were also down, from 15 to 12.

Project Reboot will see Infor's Cloudsuite Public Sector software rolled out for most aspects of council administration. 

A revised rollout schedule has led to a $1 million increase in costs, with procurement and implementation now expected to cost $11.5 million, up from an earlier $10.5 million.

The original budget was developed with the first stage implementation commencing in mid-2020 and the final implementation targeting July 2021, the council told Reseller News.

"This programme scheduling was revised over the period December 2019 to February 2020, along with the project budget. 

"The outcome of this review is a revised project schedule – still based on a first phase go-live in September 2020 and final implementation targeting July 2021."

The project scope has not been changed.

The implementation project budget assumes that the project would fund licence costs for the duration of the project and for the remainder of the subscription year following go-live. 

The revised roll out schedule means the project will be funding these licence costs for a longer period of time than anticipated in the original budget.

Overall, the status of the project is rated amber "while resourcing requirements and risks associated with overlapping go-lives and testing activities across phases two (assets), three (HCM/payroll) and four (finance and property and rating), and resourcing of testing activities over the December/January period are addressed", council said in its project commentary, also included in the agenda.

The rollout of phase one, budgeting and planning, clearly had its challenges, the commentary indicated.  

"User acceptance testing has been completed for the setup of the planning process through to the completion of budget entry, but not for the full end to end process due to issues encountered.  

"Go live activities have continued alongside planning to address the outstanding areas to be tested and preparing a fall back/parallel run option to ensure the LTP [long term plan] budgeting process is not compromised.  

"Performance issues encountered over the go live weekend are being investigated by Infor with a decision to continue with go live or fall back to the status quo solution required by 4 September."

It went on to say an Infor global team has been working on this issue as a "priority one, high level incident" and had implemented a work-around to allow go live testing to continue the week of 24th August. 

"As a priority one issue, we have received 24-hour global support to resolve the matter. A root cause analysis is being undertaken to understand the issue that has been encountered, the work around solution and delivery of a permanent fix."

However, the council told Reseller News phase one, budgeting and planning, was now live.

Ascender was selected to deliver the HR and payroll aspects of Project Reboot, however, workshops to be held with Ascender to scope the implementation have been delayed to the end of September due to resourcing constraints within the WRC and Infor team with the phase one go live, the commentary said.

Other delays are noted in the asset management and human capital management aspects of the project.

The overall aim of Project Reboot was to transform how the council operated, through the use of processes and enabling systems that were easy to use, provided ready access to information and security that the integration points will be seamless, secure and provide data integrity, the council has said.


Follow Us

Join the newsletter!

Or

Sign up to gain exclusive access to email subscriptions, event invitations, competitions, giveaways, and much more.

Membership is free, and your security and privacy remain protected. View our privacy policy before signing up.

Error: Please check your email address.

Tags Inforkpmglocal governmentWaikato Regional CouncilAscenderProject RebootCloudSuite

Events

Featured

Slideshows

Meet the Reseller News 30 Under 30 Tech Awards 2020 winners

Meet the Reseller News 30 Under 30 Tech Awards 2020 winners

This year’s Reseller News 30 Under 30 Tech Awards were held as an integral part of the first entirely virtual Emerging Leaders​ forum, an annual event dedicated to identifying, educating and showcasing the New Zealand technology market’s rising stars. The 30 Under 30 Tech Awards 2020 recognised the outstanding achievements and business excellence of 30 talented individuals​, across both young leaders and those just starting out. In this slideshow, Reseller News honours this year's winners and captures their thoughts about how their ideas of leadership have changed over time.​

Meet the Reseller News 30 Under 30 Tech Awards 2020 winners
Reseller News Exchange Auckland: Beyond the myths — how partners can master cloud security

Reseller News Exchange Auckland: Beyond the myths — how partners can master cloud security

This exclusive Reseller News Exchange event in Auckland explored the challenges facing the partner community on the cloud security frontier, as well as market trends, customer priorities and how the channel can capitalise on the opportunities available. In association with Arrow, Bitdefender, Exclusive Networks, Fortinet and Palo Alto Networks. Photos by Gino Demeer.

Reseller News Exchange Auckland: Beyond the myths — how partners can master cloud security
Reseller News welcomes industry figures at 2020 Hall of Fame lunch

Reseller News welcomes industry figures at 2020 Hall of Fame lunch

Reseller News welcomed 2019 inductees - Leanne Buer, Ross Jenkins and Terry Dunn - to the fourth running of the Reseller News Hall of Fame lunch, held at the French Cafe in Auckland. The inductees discussed the changing face of the IT channel ecosystem in New Zealand and what it means to be a Reseller News Hall of Fame inductee. Photos by Gino Demeer.

Reseller News welcomes industry figures at 2020 Hall of Fame lunch
Show Comments