Menu
NSA data center suffers 'meltdowns,' is delayed by a year, report says

NSA data center suffers 'meltdowns,' is delayed by a year, report says

The giant Utah facility has been dogged by electrical problems, a report says

A massive data center being built by the National Security Agency in Utah has been plagued by "chronic electrical surges" that have destroyed equipment and delayed its opening for a year, according to a report Monday.

The facility has suffered 10 "meltdowns" in the past 13 months that destroyed hundreds of thousands of dollars' worth of machinery, The Wall Street Journal reported Monday, citing project documents and unnamed officials.

The data center is expected to be the NSA's main facility for storing, decrypting and analyzing the vast amounts of data it collects through its surveillance programs. Those programs have been under scrutiny since the disclosures about Prism and other data collection efforts earlier this year.

The data center has cost a reported US$1.4 billion excluding the computing equipment inside, and covers more than a million square feet.

Data centers can consume huge amounts of power, partly for the compute gear but also for cooling equipment that keeps the computers from overheating.

The NSA facility, located 30 miles south of Salt Lake City in a town called Bluffdale, continuously uses 65 megawatts of electricity -- enough to power a small city -- at a cost of more than $1 million a month, the Journal reported.

The electrical problems, known as arc fault failures, create "fiery explosions, melt metal and cause circuits to fail," one official told the newspaper.

"Documents and interviews paint a picture of a project that cut corners to speed building," the Journal said. Backup generators have failed several times and the cooling system has yet to be tested, according to the newspaper.

An NSA spokeswoman told the Journal that "the failures that occurred during testing have been mitigated." But the Journal said there is disagreement about the cause of the problems and whether proposed fixes will work.

The NSA planned to turn on some of the computers at the facility this week, the Journal reported.

James Niccolai covers data centers and general technology news for IDG News Service. Follow James on Twitter at @jniccolai. James's e-mail address is james_niccolai@idg.com


Follow Us

Join the newsletter!

Or

Sign up to gain exclusive access to email subscriptions, event invitations, competitions, giveaways, and much more.

Membership is free, and your security and privacy remain protected. View our privacy policy before signing up.

Error: Please check your email address.

Tags governmentservershardware systemsNational Security Agency

Featured

Slideshows

EDGE 2018: Kiwis kick back with Super Rugby before NZ session

EDGE 2018: Kiwis kick back with Super Rugby before NZ session

New Zealanders kick-started EDGE 2018 with a bout of Super Rugby before a dedicated New Zealand session, in front of more than 50 partners, vendors and distributors on Hamilton Island.​

EDGE 2018: Kiwis kick back with Super Rugby before NZ session
EDGE 2018: Kiwis assess key customer priorities through NZ research

EDGE 2018: Kiwis assess key customer priorities through NZ research

EDGE 2018 kicked off with a dedicated New Zealand track, highlighting the key customer priorities across the local market, in association with Dell EMC. Delivered through EDGE Research - leveraging Kiwi data through Tech Research Asia - more than 50 partners, vendors and distributors combined during an interactive session to assess the changing spending patterns of the end-user and the subsequent impact to the channel.

EDGE 2018: Kiwis assess key customer priorities through NZ research
Show Comments